In true Agile fashion, we did build all of this out using Post-its:
But for a cleaner version of the Post-It wall, here it is:
- CAD approval
- Create site plan
- Apply for clearing and grading permit (we think the forestry permit is a part of this)
- Septic design
- Septic/well installation
- Locate the well
- Clear road to well
- Gravel
- Build pad for well drilling
- Well approval
- Contractor drill well (& build pumphouse, pumps and systems)
- Health department water testing
- Bring in container/shed to place on well pad
- Trenching (we will do this)
- Septic contractor install
- Finalize house design
- Building permit
- Get street address
- Electricity
- PSE Project Engineer assignment
- Trenching primary to transformer and conduit
- Site prep for transformer
- Trenching from transformer to well site & conduit
- Trench from well site to house site
- PSE install
- Cable install